Short answer: on data centre projects, delay damages are increasingly tied to milestones such as energisation and readiness, not just final completion, and often to the owner's commitments to its own tenant. Before you sign, check each milestone and its rate, the overall cap and any sub-cap, when damages stop, what excuses them, and whether your subcontracts pass the same exposure down.
Liquidated damages (LDs) are a pre-agreed amount the contractor pays for each day or week of delay. They are common on almost every construction project. On data centres they are larger, more numerous and more closely tied to commitments outside the construction contract. This guide covers how they work, where data centre contracts differ, and what to check. It is general information, not legal advice.
For the wider review, see data centre construction contracts: what to review before you sign.
Why delay damages are bigger on data centres
The owner has usually committed capacity to a tenant before the building is finished. Delivery provisions that once reflected modest rent abatements may now include daily liquidated damages, milestone penalties and termination rights tied to customer impacts (DatacenterDynamics). Data centres are built on tight schedules and often impose liquidated damages on contractors for missing milestones like energisation and "rack readiness" (Kilpatrick Townsend).
How liquidated damages are calculated
The usual mechanism is simple: a daily rate stated in the contract, multiplied by the number of days of delay (Bracewell). On data centres, the complexity sits around that calculation:
- Several rates. Different rates for different milestones, data halls or phases.
- Staggered rates. Damages that increase the longer the delay runs.
- Caps and sub-caps. An overall cap on delay damages, often below the general liability cap.
Milestones, not just completion
On an office building, LDs usually attach to one completion date. On a data centre, delivery schedules should integrate substations, transformers, generators, battery systems and cooling systems, with separate milestones for construction completion, energisation and operational readiness (Construction Dive).
Lawyers advising on data centre contracts suggest tying liquidated damages to critical-path events rather than general completion milestones, and setting cure periods and recovery schedules before LDs apply (Bracewell, via National Law Review).
For each milestone, check:
- What the milestone means. Who certifies it, and on what evidence?
- What it depends on. Is it in the contractor's control, or does it depend on the utility, owner-furnished equipment or the owner's own fit-out?
- When damages stop. At the milestone, at completion, or when integrated systems testing passes?
Caps, sub-caps and the gap down the chain
Contractors are unlikely to accept full exposure to loss of use, loss of profit and similar business losses. Typical solutions include a staggered damages set-up and a sub-cap on delay damages, with the overall cap often framed as a percentage of contract value (Reed Smith).
That creates a gap. Tenants may negotiate remedies worth tens of millions of dollars, while contractors cap liability at a percentage of contract value, equipment manufacturers at the value of the affected equipment, and design professionals at limits below the developer's exposure (DatacenterDynamics). Whoever sits in the middle of that chain carries the difference.
If you are the main contractor, compare the LDs and caps in your main contract with what your subcontracts and supply agreements pass down. If you are a subcontractor, check whether you are being asked to carry more than your share of the main contract's exposure.
Are liquidated damages enforceable?
England and Wales. The test comes from Cavendish Square Holding BV v Makdessi [2015] UKSC 67: whether the clause is unconscionable or extravagant so as to amount to a penalty (Freshfields). Commercially negotiated LDs between sophisticated parties are rarely struck down.
Two later decisions matter for phased projects like data centres:
- In Triple Point Technology Inc v PTT Public Company Ltd [2021] UKSC 29, the Supreme Court found that liability for liquidated damages survives termination of the contract (Freshfields). LDs accrue up to termination, and general damages apply after that.
- In Eco World – Ballymore Embassy Gardens Company Ltd v Dobler UK Ltd [2021] EWHC 2207 (TCC), the court did not treat a single rate of liquidated damages as automatically fatal where there was sectional completion or partial possession (Keating Chambers).
United States. Courts will often enforce LDs when they reflect a reasonable pre-estimate of damages, but may strike them when they operate as penalties (Crowell & Moring). The rules vary by state, so check the governing law.
What excuses delay damages
LDs only run for delay the contractor is responsible for. Check what the contract gives you when the cause sits elsewhere:
- Extensions of time. Which events give time, and whether they also give money.
- Owner-furnished equipment and utility delays. Whether late equipment or a late grid connection is an employer risk.
- Force majeure and government action. Whether the clause provides only an extension of time, or also excuses liquidated damages, customer credits and milestone failures (Quinn Emanuel). Moratoria and permitting changes have made this a live question in the US (Kilpatrick Townsend).
- Notice. Almost every excuse depends on giving notice in time. An extension of time you do not notify is usually an extension you do not get.
Checklist before you sign
| Check | Question |
|---|---|
| Milestones | Which milestones carry damages, and what does each depend on? |
| Rates | Daily or weekly rate per milestone, phase or data hall; staggered rates |
| Caps | Overall cap on delay damages, any sub-cap, and how it sits against the general liability cap |
| End point | When damages stop: milestone, completion or testing |
| Excuses | Extension of time events, owner-furnished equipment, utility delay, force majeure, change in law |
| Notices | The notice period for each excuse, in the main contract and in every subcontract |
| Flow-down | Whether subcontract LDs and caps match the exposure in the main contract |
| Governing law | The penalty test that applies, and any local rules on enforceability |
Where software helps
Lexilio reads the full contract suite and extracts every milestone, damages rate, cap and notice with its clause reference. It flags where a subcontract does not match the main contract, such as a shorter notice period or a different cap. The Contract Assistant answers questions such as "when do delay damages stop on this contract?" with the exact clause. Customer documents are never used to train AI models.
See how Lexilio supports data centre construction, or start a free trial.
Frequently Asked Questions
Are liquidated damages enforceable on data centre projects?
Usually, yes. In England and Wales, the Makdessi test asks whether the clause is unconscionable or extravagant. In the US, courts generally enforce LDs that reflect a reasonable pre-estimate of damages. Commercially negotiated LDs between experienced parties are rarely struck down, but the governing law matters.
Do liquidated damages stop when the contract is terminated?
Under English law, following Triple Point v PTT [2021] UKSC 29, liquidated damages accrue up to termination. After termination, the employer's remedy is general damages, assessed in the usual way.
What is a sub-cap on delay damages?
A separate, lower limit on the total liquidated damages the contractor can pay for delay, which sits inside the overall liability cap.
Can liquidated damages apply to energisation?
Yes. Many data centre contracts set separate milestones for construction completion, energisation and operational readiness, each with its own damages. Check whether energisation depends on the utility, and whether a late connection excuses the damages.
Sources
- DatacenterDynamics: The new age of contractual risk allocation in data center development
- Kilpatrick Townsend: Schedule risk of government action in data center construction
- Bracewell: Managing contractual risk in data center construction
- National Law Review: Data center delivery models and risk allocation
- Construction Dive: Guidelines for identifying key data center risk
- Reed Smith: Liability clauses in data center construction contracts
- Freshfields: Liquidated damages survive termination (Triple Point v PTT)
- Freshfields: Liquidated damages and partial possession
- Keating Chambers: Liquidated damages and London buses (Eco World v Dobler)
- Crowell & Moring: Data center risks include schedules, supply chain and labor
- Quinn Emanuel: Force majeure and the AI data center buildout