Data Centre Construction Contracts: What to Review Before You Sign

What to check in a data centre or colocation construction contract: completion and testing, delay damages, owner-furnished equipment, power and energisation, package interfaces and liability caps. FIDIC, NEC, JCT, AIA and bespoke EPC.

Lexilio Editorial·28 November 2026·10 min read

Short answer: review the dates and everything attached to them. Data centre contracts tie delay damages, milestone payments and termination rights to completion and testing dates, often while owner-furnished equipment and the power connection sit outside the contractor's control. For each date, check who carries the risk, which notice protects your position, and whether the subcontracts say the same thing as the main contract.

Data centres (data centers in the US) are now among the largest and fastest construction programmes in the UK, the Gulf and North America. The contracts behind them look familiar on the surface, but the risk sits in different places from an office or a warehouse. This guide covers which contract forms are used, the eight areas to review before signing, and a checklist for commercial teams. It is general information, not legal advice.

Why data centre contracts are different

Three things set data centre contracts apart.

The date is the product. The owner has usually committed the capacity to an end customer before construction starts. Industry commentators report that delay remedies that once reflected modest rent abatements now often include daily liquidated damages, milestone penalties and termination rights tied to customer impacts, and that power availability, energisation, commissioning, equipment lead times and operational-readiness dates are increasingly contractual commitments (DatacenterDynamics).

The building is mostly mechanical and electrical. In UK practice, M&E work can account for as much as 70% of the work involved in delivering a data centre (Gowling WLG). That puts specialist supply, installation and testing on the critical path.

The contract is a suite, not a single document. The interface between shell and core construction, fit-out contracts, long-lead supply contracts and owner and operator contracts creates a complex contractual matrix (Simmons & Simmons). Most disputes start where one of those documents does not match another.

Which contract forms are used

There is no single standard. In a 2026 industry survey by CMS, respondents reported seeing FIDIC, JCT, NEC and bespoke contracts used fairly equally, with FIDIC used slightly more often, and EPC and EPCM were the two most common contract models (CMS).

  • UK: design and build and EPC models dominate. NEC4 ECC Option A is popular with some clients but needs detailed amendments, and EPC contracts are often based on the FIDIC Yellow or Silver Book depending on how much responsibility the contractor takes (Brodies). FIDIC suits projects with a significant element of power infrastructure, while JCT and NEC forms are also frequently adopted depending on the scope and the supply chain (Burges Salmon).
  • Gulf: FIDIC-based contracts with amended Particular Conditions are widely used, as on most large projects in the region.
  • US: EPC, design-build and construction management at risk, on owner forms or AIA, ConsensusDocs and DBIA documents with extensive supplementary conditions. US-style EPC models often assume different insurance regimes and liability caps from UK practice (Brodies).

Whatever the form, expect bespoke amendments. The standard form tells you very little about where the risk has landed. The amendments tell you nearly everything.

Eight things to review before you sign

1. What "complete" means

On an office building, practical completion (substantial completion in the US) usually means the building can be occupied with minor items outstanding. On a data centre, a facility may be physically built but cannot enter service without successful integrated systems testing, and the testing regime often decides when practical completion can be certified, when delay damages stop and when security or retention is released (Brodies).

Check whether completion is tied to construction, to each commissioning level, or to integrated systems testing. Check whether the date for completion is for the whole facility or by data hall or phase.

2. Delay damages and milestones

Find every date that carries a consequence: the rate of delay damages, the cap, any milestone damages, and any termination right linked to delay. Then check when damages stop. If they run until integrated systems testing passes, the contractor carries time that may depend on equipment and systems it did not supply.

See liquidated damages and milestone dates on data centre projects.

3. Owner-furnished equipment

Owners often buy generators, switchgear, UPS systems and cooling plant directly and hand them to the contractor to install, known as owner-furnished, contractor-installed (OFCI) equipment. It can reduce the contractor's supply chain risk (Simmons & Simmons), but it creates new questions: who carries the delay if it arrives late, who carries a defect found on installation, and who has recourse against the vendor. Where equipment is owner-furnished, the contractor may have no direct contractual recourse against the vendor (Fenwick Elliott).

Check that late or defective owner-furnished equipment gives the contractor time and money, and what notice the contract requires to claim them.

4. Long-lead procurement

Equipment lead times drive the programme. Owners may place early purchase orders for long-lead equipment and agree installation, integration and testing scope later (Wiss). Check how those early orders transfer into the main contract, who carries price movement and tariffs, and whether the programme the contract relies on assumes lead times that the market can actually deliver.

5. Power, utility connection and energisation

A finished data centre without power cannot be handed over. Grid connection delays pose significant risks to construction timelines (Simmons & Simmons), and who pays when power does not arrive on time is now a live litigation question in the US (Foley & Lardner).

Check whether a late utility connection is an employer risk event, a compensation event or a relevant event, whether it gives time only or time and money, and whether energisation is a condition of completion.

6. Commissioning and integrated systems testing

Data centre commissioning usually runs through component verification, system testing, integrated systems testing and reliability or soak testing (Brodies). Many projects describe this as five levels, from factory acceptance testing (Level 1) to integrated systems testing (Level 5).

Check who writes the test scripts, who witnesses them, how many attempts are allowed, and who carries the cost and time of a failed test when several suppliers' systems are involved.

7. Interfaces between packages

Where shell and core and fit-out are let separately, the shell contractor needs clear obligations on loadings, penetrations, spatial allowances and temporary works for later trades (Brodies). The same applies down the supply chain.

Read the subcontracts against the main contract. The classic gap is a notice period: 28 days to notify the employer under the main contract, but only 14 days given to the subcontractor, or the other way round. Check scope descriptions that say "as shown" against the drawings they reference. See where scope gaps hide between the specification and the drawings.

8. Liability caps, data and service credits

Building contracts on JCT or NEC forms have not traditionally set an overall cap on the contractor's liability, unlike engineering contracts on FIDIC or similar forms, where a cap is typically set by reference to the contract sum (Reed Smith). On data centres, owners may also seek to extend the contractor's liability to data loss or service credits owed to their own customers.

Check the overall cap, what sits outside it, any indemnity for data loss or outages, and whether consequential loss is excluded. See uncapped indemnity in construction contracts.

Regulation and approvals

Approvals can stop a project after the contract is signed. In the US, Hill County, Texas imposed a moratorium on data centre construction in May 2026, and on 14 July 2026 New York became the first state to impose a statewide moratorium on large data centre construction (Kilpatrick Townsend). Check how the contract treats a change in law, a moratorium or a refused approval: whether it is an excused event, who carries the cost of suspension, and whether either party can terminate.

In the UK, data centres were designated as Critical National Infrastructure on 12 September 2024 (GOV.UK). Expect security, vetting and access requirements in the contract, and check that their cost and time are allowed for.

Data centre contract review checklist

AreaWhat to check
CompletionIs completion tied to construction, a commissioning level or integrated systems testing? Whole facility or by phase?
Delay damagesRate, cap, milestone damages, when damages stop, termination for delay
Owner-furnished equipmentTime and money for late or defective supply, notice required, recourse against the vendor
Long-lead procurementTransfer of early orders, price and tariff risk, realistic lead times in the programme
Power and energisationWho carries a late utility connection, time only or time and money, condition of completion
CommissioningTest scripts, witnessing, retests, cost of failure across multiple suppliers
InterfacesSubcontract notice periods and scope against the main contract, shell and core against fit-out
LiabilityOverall cap, carve-outs, data loss and service credits, consequential loss
RegulationChange in law, moratoria, refused approvals, security requirements

For the general pre-contract review, see the construction contract review checklist.

Where software helps

Lexilio reads the full contract suite for a data centre project, including the main contract, subcontracts, supply agreements, specifications and drawings, and extracts every obligation, deadline and notice with its clause reference. It flags where one document contradicts another, such as a notice period in the main contract that the subcontract shortens. The Contract Assistant answers questions such as "who carries the delay if owner-furnished switchgear arrives late?" with the exact clause, and can draft the notice from the obligation it triggers. Lexilio reads FIDIC, NEC, JCT, AIA, EJCDC and bespoke EPC contracts, including Particular Conditions, Z clauses and amendments. Customer documents are never used to train AI models.

See how Lexilio supports data centre construction, or start a free trial with your own contract.


Frequently Asked Questions

What contract is used for data centre construction?

There is no single standard. FIDIC, NEC, JCT and bespoke contracts are all widely used, usually with heavy amendments. EPC and EPCM are the most common models. In the US, owners use EPC, design-build and construction management at risk, often on owner forms or AIA, ConsensusDocs or DBIA documents.

Who should review a colocation or data centre construction contract?

The commercial team should review the risk allocation, dates, notices and payment terms, and a construction lawyer should review the amendments, liability position and anything the team is unsure about. Software can give a fast first pass across the whole suite so that both spend their time on the clauses that matter.

Who carries the risk if owner-furnished equipment arrives late?

It depends on the contract. Well-drafted contracts make late or defective owner-furnished equipment an employer risk that gives the contractor time and money, subject to notice. Heavily amended contracts may shift some of that risk to the contractor. Check the relevant event, compensation event or change provisions and the notice period that applies.

When do delay damages stop on a data centre project?

When the contract says completion has been achieved. On many data centre projects that is linked to integrated systems testing rather than to the building being physically complete, so damages can continue while testing is outstanding.

What is integrated systems testing (IST)?

The final stage of commissioning, which tests how the facility's power, cooling and control systems perform together under operating and failure conditions, rather than testing each piece of equipment in isolation.