Construction Notice Deadlines: NEC, FIDIC, AIA, EJCDC and JCT Compared

How long you have to give notice under NEC4, FIDIC, AIA A201, EJCDC and JCT, what counts as a valid notice, and what to look for in software that tracks construction notice deadlines.

Lexilio Editorial·15 November 2026·8 min read

Most construction claims are lost on timing before anyone argues about merit. A notice goes out late, goes to the wrong address, or is not recognisable as a notice, and the entitlement is gone. The deadline differs by contract, and amendments change it again.

This guide sets the main notice deadlines side by side for NEC4, FIDIC, AIA, EJCDC and JCT, explains what makes a notice valid, and lists what to look for in software that claims to catch these deadlines. It is general information, not legal advice. Always read the clause in your own contract and its amendments.

Notice deadlines at a glance

ContractEventTime limitClause
NEC4 ECCContractor notifies a compensation event8 weeks from becoming aware61.3
FIDIC 1999 Red and Yellow BooksContractor notifies a claim28 days20.1
FIDIC 2017Either party notifies a claim28 days from becoming aware, or when they should have become aware20.2
AIA A201-2017Notice of Claim21 days15.1.3.1
AIA A201-2017Concealed or unknown conditions14 days from first observance3.7.4
EJCDC C-700 (2013)Change proposal30 days after the start of the eventChange proposal provisions
JCTNotice of delay and loss and expensePrompt written notice, no single fixed number of daysVaries by edition

Always confirm the figure against your signed contract. Employers in the Gulf, in particular, often shorten the FIDIC period by amendment.

NEC4: eight weeks, and early warnings do not count

Under clause 61.3 of the NEC4 Engineering and Construction Contract, the Contractor does not notify a compensation event once more than eight weeks have passed since it became aware of the event. Clause 61.3 is a frequent adjudication issue. NEC guidance points out that early warnings and meeting minutes are unlikely to be accepted as proof of compliance, and that a notification should be sent separately from other communications so the recipient can tell what it is for.

Two practical points follow. First, work out the date the Contractor became aware of the event, because the eight weeks run from there and not from the date of the instruction. Second, record the notification itself: who sent it, to whom, when, and in what form.

For the compensation event process end to end, see NEC clause 60 compensation events.

FIDIC: 28 days, and the notice must be recognisable

Under FIDIC 1999, sub-clause 20.1 requires the Contractor to give notice of a claim within 28 days. Missing it means losing entitlement to that claim. FIDIC 2017 keeps the 28-day period, applies it to both Contractor and Employer, and tightens the form: a Notice must be in writing, signed by an authorised representative, identified as a Notice, and delivered to the address in the Contract Data. Progress reports and programmes do not replace it.

Employer amendments often shorten the period or add conditions. Our guide to FIDIC Red Book clause 20 notice deadlines goes through the clause.

AIA and EJCDC: short windows in the US forms

AIA A201-2017 requires a Notice of Claim within 21 days, including payment disputes that are treated as claims. For concealed or unknown conditions the period is shorter: 14 days from first observance. EJCDC C-700 (2013) requires a change proposal no later than 30 days after the start of the event.

Subcontracts add a second layer. AIA A401 has the subcontractor assume toward the contractor the obligations the contractor assumes toward the owner, so a subcontractor works to the prime contract windows even if the subcontract does not repeat them. See our guide to subcontractor agreement review and Lexilio for the US market.

JCT: prompt notice, and payment notices on top

JCT forms generally ask for prompt written notice of delay and set their own requirements for loss and expense claims, rather than a single fixed number of days. In England and Wales, the Construction Act adds a separate layer of payment notices and pay less notices with their own timing. A late pay less notice can leave the payer owing the notified sum. See Lexilio for the UK market.

What makes a notice valid

Across all of these forms, the same questions decide whether a notice works:

  • Trigger date. The date the event happened, or the date you became aware or should have become aware.
  • Addressee. The person or address the contract names, often in the Contract Data.
  • Form. Written, sometimes signed, sometimes required to say it is a notice under a named clause.
  • Content. Enough to identify the event and the clause relied on.
  • Delivery method and proof. Email, courier or registered post, and a record of when it was sent.

A notice that fails on any of these can be challenged even if it went out on time.

What to look for in notice deadline software

Several products now promise to catch notice deadlines. They differ more than their marketing suggests. Before choosing one, ask:

  1. Does it read your actual contract, including amendments? A tool that applies the standard-form period will give you the wrong date on an amended contract.
  2. How does it set the trigger date? Awareness, event date and instruction date are different starting points.
  3. Which sources does it work from? Some tools work from the contract and the documents you upload. Others also monitor email or site records. Check exactly which, and whether you want your inbox connected.
  4. Does it handle the whole contract chain? A subcontract deadline that is shorter than the main contract needs to be visible in both.
  5. Does it prepare the notice? The right clause, the right addressee and the contract's own wording save time and reduce mistakes.
  6. Is there a record? You need to show what was issued and when.
  7. Does a person verify the output? Treat every AI-identified deadline as needing human confirmation.

Test any tool on a real contract with amended notice periods, and confirm in writing that your documents are not used to train AI models.

Where Lexilio fits

Lexilio reads FIDIC, NEC, JCT, AIA, EJCDC and ConsensusDocs-style contracts, including Particular Conditions, Z clauses and bespoke amendments, and it reads scanned PDFs and tracked changes in Word. Upload the contract suite and it builds an obligations, deadlines and notices register with real dates and clause references, so the notice period you work to is the one in your signed contract, not the standard form.

When a notice is due, Lexilio drafts it from the obligation that triggers it, in the contract's own wording. Once it goes out, you record it as served with the date, the method and who served it, so the record question above has an answer. Obligations and notices can be assigned to named people on the team, every action is kept in an immutable audit log, and a subcontract notice period that is shorter than the main contract allows shows up as a conflict between the documents.

Lexilio works from the contracts and documents you upload. Customer documents are never used to train AI models.

Start a free trial and upload a contract to see its notice register. For the FIDIC periods on one page, see the FIDIC notices and time bars cheat sheet. If you work on subcontracts, see how Lexilio helps subcontractors.


Frequently Asked Questions

How long do I have to notify a compensation event under NEC4?

Under clause 61.3 of the NEC4 ECC, the Contractor does not notify a compensation event once more than eight weeks have passed since it became aware that the event had happened. Check your Contract Data and Z clauses, because amendments can change the position.

What is the notice deadline for a claim under FIDIC?

Sub-clause 20.1 of the FIDIC 1999 Red and Yellow Books requires notice within 28 days. FIDIC 2017 keeps 28 days, runs it from when the party became aware or should have become aware, and applies it to both parties. Employer amendments often shorten it.

What is the AIA A201 notice period for claims?

AIA A201-2017 requires a Notice of Claim within 21 days under section 15.1.3.1, and notice of concealed or unknown conditions within 14 days under section 3.7.4.

Can software catch construction notice deadlines?

Software can read the notice periods in your actual contract, build a register of them, draft the notices and keep a record of what was served. How far it goes beyond that, for example monitoring email, varies by product, and a qualified person should verify every deadline.