How to Assess a Delay or Disruption Claim: An Entitlement Checklist

How to assess whether a construction delay or disruption claim has entitlement under FIDIC, NEC, JCT and AIA: the event, the notice, causation, concurrency, records and quantum, and who should assess each part.

Lexilio Editorial·28 November 2026·9 min read

Short answer: assess entitlement before quantum. A delay or disruption claim needs four things: an event the contract puts at the other party's risk, a notice given in time and in the right form, proof that the event caused the delay or disruption, and records that support the amount. If any one is missing, the claim usually fails, however real the delay was.

Most delay claims are lost on entitlement, not on numbers. The programme analysis can be excellent and the costs well recorded, but if the event was at the contractor's risk or the notice was late, the claim goes nowhere. This guide sets out a checklist for assessing a delay or disruption claim under the main standard forms, and who should assess each part. It is general information, not legal advice.

Delay and disruption are different claims

  • Delay is about time: the completion date moves. The claim is for an extension of time, and often for the cost of the longer period (prolongation).
  • Disruption is about productivity: the work takes more effort than planned, whether or not the completion date moves. The claim is for the cost of the lost productivity.

A single event can cause both. They are proved differently, so assess them separately.

Step 1: Identify the event and who carries the risk

Start with the contract, not the programme. Find the clause that makes the event the other party's risk:

FormWhere the risk events are listed
FIDIC 2017Sub-Clause 8.5 (extension of Time for Completion) and the clauses it refers to
NEC4 ECCClause 60.1 compensation events, plus any added by secondary Options or Z clauses
JCT SBC 2016Clause 2.29 Relevant Events (time) and the Relevant Matters (loss and expense)
AIA A201-2017Section 8.3.1 (delays and extensions of time) and Article 15 (claims)

Then check the amendments. Particular Conditions, Z clauses and schedules of amendments often delete or narrow the standard risk events. See what is a compensation event? NEC4 clause 60 explained.

Step 2: Check the notice

Notice is where most claims die. Find the notice clause, the period and the form it requires:

FormNotice requirement
FIDIC 2017Notice of Claim within 28 days of becoming aware, or when the contractor should have become aware, under Sub-Clause 20.2.1. A fully detailed Claim follows within 84 days under 20.2.4
NEC4 ECCNotify within eight weeks of becoming aware of the event, under clause 61.3
JCT SBC 2016Written notice forthwith when it becomes reasonably apparent that progress is being or is likely to be delayed, under clause 2.27
AIA A201-2017Claims initiated within 21 days after the event, or within 21 days after the claimant first recognises the condition, whichever is later, under Section 15.1.3.1

Check whether the notice was given to the right person, in the form the contract requires, and whether any amendment shortened the period. For a full comparison, see construction notice deadlines by contract.

Step 3: Prove causation

The event has to have caused the delay to completion, not just delay to some activity. That usually means showing the event affected the critical path.

The Society of Construction Law's Delay and Disruption Protocol (2nd edition, February 2017) is the most widely used guide in the UK and internationally. It no longer prefers one method of delay analysis, and instead explains how to choose an appropriate method for the contract, the project and the records available (White & Case). It also promotes the submission and assessment of extension of time claims during the project, rather than waiting until the end (Addleshaw Goddard).

Step 4: Deal with concurrency

Concurrent delay is the occurrence of two or more delay events at the same time, one an employer risk event and the other a contractor risk event, whose effects are felt at the same time. The Protocol treats true concurrency as rare (SCL Protocol commentary).

Where concurrent delay does occur, the Protocol's position is that the contractor's delay should not reduce the extension of time due for the employer's delay (Fenwick Elliott). Recovering money for the concurrent period is harder, and the contract may deal with concurrency expressly. Check for a concurrency clause before you assess.

Step 5: Prove disruption

Disruption claims need evidence of lost productivity. The Protocol's 2nd edition lists several ways of proving it, not only the "measured mile" approach, which compares productivity in an unaffected period with an affected one (Building). The measured mile was accepted in the Queensland case of Santos Ltd v Fluor Australia Pty Ltd in 2017 (Fenwick Elliott).

Step 6: Check the records and the quantum

Quantum follows entitlement. The usual heads are prolongation costs, disruption costs, acceleration costs and finance charges, each linked to the event that caused it.

Be careful with global claims, which claim a total loss without linking each cost to a cause. The Protocol warns that a global claim risks failing entirely if any material part of the loss was caused by a factor the employer does not bear (Fenwick Elliott).

Records decide most claims. FIDIC 2017 defines contemporary records as records prepared or generated at the same time as, or immediately after, the event (Fenwick Elliott). Programme updates, daily diaries, labour allocation and correspondence made at the time carry far more weight than a reconstruction prepared later.

Entitlement checklist

CheckQuestion
EventIs the event listed as the other party's risk, after the amendments?
NoticeWas notice given in time, in the right form, to the right person?
Further particularsWere the detailed claim and updates submitted on time?
CausationDid the event delay completion, or only a non-critical activity?
ConcurrencyWas there contractor delay at the same time, and does the contract deal with it?
DisruptionIs there evidence of lost productivity that can be linked to the event?
RecordsAre there contemporary records for the delay and the costs?
QuantumIs each head of cost linked to a cause, or is it a global claim?

Who should assess a construction claim?

Different parts need different people:

  • The quantity surveyor or commercial manager owns the claim: entitlement under the contract, notices, records and quantum.
  • A planning or delay expert proves causation and analyses concurrency, usually with the programme and progress records.
  • A claims consultant often prepares or reviews the full submission on larger claims.
  • A construction lawyer advises where entitlement turns on the meaning of the contract, a time bar or a dispute about the amendments.

See also who can review a construction contract claim.

Where software helps

Lexilio checks the entitlement side against the contract itself. It reads the main contract, subcontracts and amendments, finds the risk event and notice clauses that apply, and shows the notice period and form required, with the clause reference. The Contract Assistant answers questions such as "is late access a compensation event under this contract, and what notice is required?" with the exact clause, and Lexilio can draft the notice from the obligation it triggers. It does not carry out delay analysis or replace a planning expert. Customer documents are never used to train AI models.

Start a free trial with the contract behind your claim.


Frequently Asked Questions

Who can assess construction disruption claims?

Usually the quantity surveyor or commercial manager first, for entitlement and records, then a delay or productivity expert to prove the loss of productivity, and a construction lawyer where entitlement is disputed. Software can check the contract entitlement and notice requirements quickly before the experts are engaged.

How do you evaluate whether project delays support a construction claim?

Check four things in order: that the event is the other party's risk under the amended contract, that notice was given in time, that the event caused delay to completion, and that there are records to support the time and cost. If the first two fail, the claim usually fails regardless of the delay analysis.

What is the difference between a delay claim and a disruption claim?

A delay claim is about time and the cost of a longer project. A disruption claim is about lost productivity, whether or not completion is delayed.

Does concurrent delay defeat an extension of time?

Under the SCL Protocol approach, no: the contractor's concurrent delay should not reduce the extension of time due for the employer's delay. Recovery of money for the concurrent period is harder. The contract may say otherwise, so check for an express concurrency clause.